Work in Progress:
Completed first lift pour for elevator #2 (South).
Completed first lift pour for stair tower #3.
Grade beams and pile caps along column line 17 are complete.
Steel clips for sequence 1-4 are complete.
Steel erection for sequence 1-4 is in progress.ā¦
Work in Progress:
Continuing the steam and condensation piping in the East Mechanical room.
Heating and snow melt piping is continuing in the West Mechanical room.
Continuing with the chilled water piping in the West mechanical room.
Working on plenum duct at AHU-1 in Eastā¦
Two Āé¶¹¹ū¶³ researchers from the College of Arts and Sciences have been awarded more than $1 million in federal grants for their research projects.
The National Institutes of Healthās National Institute on Aging awarded Gemma Casadesus-Smith, Ph.D., from Kentā¦
Āé¶¹¹ū¶³, in partnership with the University of Akron, will present a āWhy Polling Still Mattersā forum at 5:30 p.m. on Monday, April 25, in the Kent Student Center Ballroom Balcony as part of the āPolitically Speakingā public forum series discussing the upcomingā¦
Āé¶¹¹ū¶³ās Ohio Employee Ownership Center (OEOC) will host the 30th Annual Ohio Employee Ownership Conference on Friday, April 29, at the Hilton West in Fairlawn, Ohio. The theme for the conference is āCelebrating Three Decades of Success: Growing the Employeeā¦
Work in Progress:
Start forming elevator #2 (south).
Grade beam and pile caps along column line #17 between A and G is in progress.
Pile caps for elevator #2 are complete.
Installing pile caps for Stair #3.
Looking forward:
Steel erection sequence #1 will begin onā¦
Āé¶¹¹ū¶³ will host the annual international conference of the Institute for Complex Adaptive Matter on May 16-18 at the Āé¶¹¹ū¶³ Hotel and Conference Center.
Work in Progress:
Pulling wire throughout for branch circuits.
Installing duct on 1st floor.
Complete domestic water rough-in on the 2nd floor.
Sanitary piping rough-in has been completed on the 3rd floor.
Completing remaining framing throughout.
Starting door frameā¦
Work in Progress:
Forming lift 3 on elevator #1.
Working on retaining wall progressing south to column line A7.
Pile caps and foundations for elevator #2 are complete.
Looking forward:
Pour lift #3 on elevator #1 on 4/8/2016.
Steel delivery and erection begins forā¦