4/21- ISB/Williams Hall Construction Updates

Work in Progress: Completed first lift pour for elevator #2 (South). Completed first lift pour for stair tower #3. Grade beams and pile caps along column line 17 are complete. Steel clips for sequence 1-4 are complete. Steel erection for sequence 1-4 is in progress. Looking forwar…

Tags: Sciences Renovation

College of Arts & Sciences

4/21- Cunningham Hall Renovation Updates

Work in Progress: Continuing the steam and condensation piping in the East Mechanical room. Heating and snow melt piping is continuing in the West Mechanical room. Continuing with the chilled water piping in the West mechanical room. Working on plenum duct at AHU-1 in East Mechanical Roo…

Tags: Sciences Renovation

College of Arts & Sciences

4/14- ISB Construction Updates

Work in Progress: Start forming elevator #2 (south). Grade beam and pile caps along column line #17 between A and G is in progress. Pile caps for elevator #2 are complete. Installing pile caps for Stair #3. Looking forward: Steel erection sequence #1 will begin on Monday, Apri…

Tags: Sciences Renovation

College of Arts & Sciences

4/7- ISB/Williams Hall Construction Updates

Work in Progress: Forming lift 3 on elevator #1. Working on retaining wall progressing south to column line A7. Pile caps and foundations for elevator #2 are complete. Looking forward: Pour lift #3 on elevator #1 on 4/8/2016. Steel delivery and erection begins for sequence #1 …

Tags: Sciences Renovation

College of Arts & Sciences

4/7- Smith Hall Renovation Updates

Work in Progress: Pulling wire throughout for branch circuits. Installing duct on 1st floor. Complete domestic water rough-in on the 2nd floor. Sanitary piping rough-in has been completed on the 3rd floor. Completing remaining framing throughout. Starting door frame installation. D…

Tags: Sciences Renovation

College of Arts & Sciences

3/24- Williams Hall/ISB Construction Updates

Work in Progress: Working on pile caps and grade beams.  Plan to start column line 17 (Southern most column line) next week. Started working on forming elevator #2 (South). Pouring elevator #1 second lift (North) today. Continuing the installation of the basement concrete retaining …

Tags: Sciences Renovation

College of Arts & Sciences

3/24- Smith Hall Renovation Updates

Work in Progress: First floor restroom and offices duct layout is complete with HVAC piping and duct installation has begun. Room 101 & 104 electrical rough-in is at 90% complete. Machine Shop electric panel installed and completed on Saturday 3/19. Room 223 electrical floor boxes ar…

Tags: Sciences Renovation

College of Arts & Sciences

3/24- Cunningham Hall Renovation Updates

Work in Progress: Steam piping in the 3rd floor east mechanical room is 20% complete. Steam condensate lines for the steam station and AHU#1 are in progress. Started installation of piping and duct work from AHU#2 in the 3rd floor west mechanical room to the addition has begun. Tie-in fr…

Tags: Sciences Renovation

College of Arts & Sciences

3/17- Smith Hall Renovation Updates

Work in Progress: New restroom plumbing rough-in nearly complete. Sheet metal duct rough-in has begun on the first floor and the new restroom areas. Electrical floor boxes are 75% complete in 223. Sanitary drain and toilet carriers are complete in the second floor. 3rd floor abatement …

Tags: Sciences Renovation

College of Arts & Sciences

3/17- Cunningham Hall Renovation Updates

Work in Progress: Chilled water service in the 3rd floor east mechanical room is 95% complete by EOB on 3/18.  Will be ready for cooling system startup on 4/15. Currently insulating the chilled water pipes in the 3rd floor wast mechanical room. Steam reducing station in the 3rd floor …